Scientific design saves time
As already mentioned above, we will never merely display information in our products. Our team of experts has extensive experience. They will design scientifically and arrange for Construction-Manager actual exam that are most suitable for users. In the study plan, we will also create a customized plan for you based on your specific situation. We have always believed that every user has its own uniqueness. In order to let you have a suitable way of learning. The staff of Construction-Manager study materials also produced three versions of the system. In our products, content, versions and plans are the best for you. You only need to purchase Construction-Manager learning guide. You can own the most important three points in your study! As you know, the best for yourself is the best. Choosing the best product for you really saves a lot of time! Construction-Manager actual exam look forward to be your best partner.
People around you are improving their competitiveness in various ways. Haven't you started to move? You must be more efficient than others before you can do more and get more pay! Construction-Manager study materials will tell you that in a limited time, you can really do a lot of things. Of course, the quality is also very high. You have to believe that the quality content and scientific design of Construction-Manager learning guide can really do this. You can easily find out that there are many people who have benefited from Construction-Manager actual exam. Next, let me tell you what other Construction-Manager study materials can't be ignored.
Detailed content, highlighted
In order to provide users with the most abundant learning materials, our company has collected a large amount of information. And set up a professional team to analyze this information. Construction-Manager study materials contain absolutely all the information you need. However, we will never display all the information in order to make the content appear more. Construction-Manager learning guide just want to give you the most important information. This is why Construction-Manager actual exam allow you to take the exam in the shortest possible time. After you enter the examination room and get the exam paper, you must be sighed that the gold content of Construction-Manager learning guide is too high. Construction-Manager study materials are really magic weapon for you to quickly pass the exam.
Respect users and protect privacy
Construction-Manager study materials are the product for global users. Standards in all aspects are also required by international standards. In terms of privacy that everyone values, we respect every user. Our company has always put the customer first as a development concept. The system designed of Construction-Manager learning guide by our IT engineers is absolutely safe. Your personal information will never be revealed. Of course, Construction-Manager actual exam will certainly not covet this small profit and sell your information. Construction-Manager study materials can come today. With so many loyal users, our good reputation is not for nothing. In us, you don't have to worry about information leakage. Selecting a brand like Construction-Manager learning guide is really the most secure.
CMAA Construction-Manager Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Topic 1: Contract Administration | 10% | - Claims and Disputes
|
| Topic 2: Risk Management | 10% | - Risk Mitigation
|
| Topic 3: Time Management | 10% | - Delay Analysis
|
| Topic 4: Professional Practice | 10% | - Leadership and Communication
|
| Topic 5: Safety Management | 10% | - Safety Programs and Policies
|
| Topic 6: Cost Management | 10% | - Value Engineering
|
| Topic 7: Technology | 5% | - Construction Technology
|
| Topic 8: Program & Project Management | 20% | - Resource Management
|
| Topic 9: Sustainability | 5% | - Green Building Practices
|
| Topic 10: Quality Management | 10% | - Quality Assurance and Control
|
CMAA Certified Construction Manager (CCM) Sample Questions:
1. As the owner's rep, a CM is providing on-site construction management services to a municipality for their new design-build city mall project.
The state requires a 40-hour value engineering workshop for all projects over $10 million. What are the key talking points about the VE process that the CM will highlight to the city's director of public works?
A) Scope reduction will reduce overall project budget.
B) Life cycle and maintenance costs should not be considered.
C) A multi-discipline review on functions and alternate solutions.
D) Interface with the design-build team is not needed at this time.
2. An owner requests a cost estimate for a project during the design phase with an estimated present-day budget of $10M. Construction is scheduled for 24 months. Escalation is 5% for the project duration. What is the projected cost for the project?
A) $10,500,000
B) $11,000,000
C) $5,375,000
D) $5,187,500
3. Which of the following statements BEST describes the recommended approach CMs should take with respect to building information modeling (BIM)?
A) The CM should not discuss BIM unless requested by the owner.
B) The CM should require the owner to use BIM.
C) The CM should not recommend the use of BIM.
D) The CM should assure the owner has considered using BIM.
4. When the CM assists the owner in prequalifying, evaluating, or screening potential contractors, especially as it relates to safety programs, the CM should evaluate the contractor's lost time frequency rate; lost time severity average; OSHA 200; OSHA 300; experience modification rate; and an up-to-date list of any OSHA citations issued to them in the last three years, including the disposition of each citation. This is important because:
A) a contractor with a poor safety record may increase the owner's risk and worker compensation costs.
B) contractors only monitor safety if they understand the owner's emphasis on safety.
C) extensive documentation is required to demonstrate sufficient due diligence.
D) a contractor with a poor safety record is likely to be a low bidder.
5. During the design phase, the CM should perform which of the following tasks?
A) Review contract milestones, payment procedures, and communication procedures.
B) Review plans, final Right-of-Way (ROW) documents, and as-built submittals.
C) Review cost estimate, schematic design, and scheduling conferences with regulatory agencies.
D) Review staffing assignments, labor affidavits, and historical trust.
Solutions:
| Question # 1 Answer: C | Question # 2 Answer: B | Question # 3 Answer: D | Question # 4 Answer: A | Question # 5 Answer: C |